Tours Home
Blackforest ICF Foundation
WHS Building Trades House
Wait Residence
Garage w/ Walkout
660 Chipmunk
Green Residence
Pilant Residence
Levy Residence
2006-2007 Widefield High School Building Trades Home
The Open House held on Friday, May 11th was a success. Attendees included County Commissioner, Dennis Hisey, state representative Marsha Looper and the director of Pikes Peak Regional Building Department, Henry Yankowski, who personally delivered the Certificate of Occupancy. Dan Vogel and the students presented the keys to Widefield School District 3's school board president, Martin Kuhn. Students grilled burgers and hot dogs as visitors enjoyed a variety of sweets.
May 1 through May 8, 2007: Students finish out trim work and touch-ups
April 14-18: Exterior stucco and interior texture is finished and students begin trim work.
April 2-11, 2007: Exterior stucco work begins and the interior is drywalled and taped
February 21, 2007 : Windows and doors are installed, roofing is completed, and students continue framing in basement
February 16: Trusses are installed and roof sheathed while students frame interior basement walls
February 7: Upper walls are poured and students are a big step closer to getting dried in
Holiday cheer at the jobsite

December 15: Garage and basement slabs are poured and students continue building walls
November 27 - December 11:
Students coated the foundation with sealer, put in the periferal drain around the foundation and installed the window wells.
Other students continued to build the upper walls.
By Monday, December 11th, New Generation Homes excavators had back-filled around the foundation and students continued working on the upper walls.
The temporary bracing was removed in the basement, allowing crews from Johnson Plumbing and Heating to work on installing the in-floor heat.
November 21: Pouring concrete foundation and main floor slab
Johnson Plumbing and Heating completed the necessary plumbing and passed the inspection on Monday, clearing the way for Tuesday's pour.
The tubing running along the Lite-Deck is the in-floor radiant heat.
Students start early, some as early as 6:45 am, so they can finish plating areas that need extra support before the concrete truck arrives from Rocky Mountain Premix. OSB is used to plate any area that could potentially blow-out during the pour.
Mr. Vogel goes over procedures and makes sure all the students understand what they need to do when the pour begins.
The concrete pour starts at around 10:30 am.
The only actual blow-out happens shortly after they begin and is quickly repaired.
The concrete is poured in 4-foot lifts. As the students maneuvering the pump hose move around the foundation, students are following them around below and hitting the walls with pieces of 2X4 to help the concrete settle
The sun is setting as the flatwork is completed by Acosta Concrete.
These pictures indicate that the areas around the plumbing and holes for electrical are properly sealed allowing no concrete to flow through.
November 17: Leveling the Lite-Deck and finishing up with the last layer of block before next week's pour
November 15: Building rebar main beam used to support the main floor and Lite-Deck, building bay windows
October 30-November 10: Laying out plumbing base, putting up ledger board for temporary support beams, setting temporary beams, bracing and Lite-Deck
October 23-27: Building T-Walls (butress walls) and bracing
October 5-20: Setting more blocks and installing V-Buck (vinyl window buck)
October 1-5: Completing footers and setting first level of blocks
Construction Zone Newsletters:
November 9, 2006
November 16, 2006
November 28, 2006
December 21, 2006
May 1, 2007