Blackforest ICF Foundation
Widefield HS Building Trades House
Wait Residence
Garage with Walkout
660 Chipmunk Rancher
ICF Garage with Walkout Basement
May 15, 2008: One last look at the "Garage Mahal" at night.
April 27, 2008: The radiant system.
April 27, 2008: Can lights are in, interior is drywalled, textured and painted. Concrete floors are stained.
Exterior details are finished to match the existing home.
April 8, 2008: Driveway and sidewalks are put in by Araco Concrete Contractors.
March 25, 2008: Color coat of stucco is applied & stonework finished to match existing house. Truss insulation & electrical is put in.
March 1, 2008: Base coat of stucco is applied, garage door, windows and doors are installed and interior framing is completed.
January 4, 2008: Trusses are on and sheeted, work on baseement in floor heat begins.
November 29, 2007: Upper ICF walls are poured.
November 10, 2007: Periferal drain is installed around the foundation.
October 31, 2007: foundation and upper slab pour are completed.
October 26, 2007: Radiant tubing is installed, plumbing base completed and preparations for foundation pour are made.
September 26, 2007: Crew Begins to Stack ICF Block
September 10 - 12, 2007: Footers are Installed and Poured
August 28, 2007: Excavation in Progress